Check cryogen levels on a system with a helium level meter
About this task
IEC 60601-2-33: 201.7.9.2.101 ff
It is very important to check and record the helium level. Sufficient helium is necessary to avoid accidental quench. Frequent checks of cryogen levels must be carried out by the responsible organization. The responsible organization is the entity accountable for the use and maintenance of your MR system. It can be, for example, a hospital, an individual clinician or a layperson. If the helium levels fall below 60%, or the level your service engineer says is acceptable, contact a service engineer immediately.
Use this procedure to check cryogen levels.